The project completion rate reached 100% and sales implementation reached 75%.
In the heart of Dammam city and in one of its most beautiful and oldest suburbs, where there is tranquility, security and integrated services. Our latest residential project [Trust Villa III] has been implemented in Al Rawdah district with areas starting from 312.5 m2 with updated and new designs to meet the desires of our valued customers.
The project has been completed at 100% and sales have reached 75%.
Accordion Content
The construction works of the project have been completed and the project has been delivered. Sales have reached more than 75% and there are ongoing reservations from customers, as the project has received high demand from those interested in owning property in the area.
Date
18/05/2023
The project completion rate reached 95% and sales execution reached 25%.
Accordion Content
With the project nearing completion and the increasing demand for Trust Villas projects, reservations for the Trust Villas Project, Phase 3, were launched on 01/07. Sales of 25% of the project have been completed and reservations are valid.
Date
28/02/2023
The percentage of internal works reached 50% and the project is close to being ready
Sales amounting to 40% of the project were implemented as demand for the project continued and coincided with the project being almost ready to receive it.
Finishing works have reached more than 50% and we have started receiving reservations and requests for interest from customers.
Date
07/01/2023
Date
30/11/2022
The structural completion rate reached 80% and the interior works have begun.
Date
12/10/2022
The project completion rate reached 10%.
Thank God, the show apartment was inaugurated in the Al-Thiqa Residential Complex and Sales Center project, in preparation for receiving customers and receiving reservations. At the same time, a Wafi license (off-plan sales) was issued, as the company was qualified to be one of the most important companies in the region and to facilitate the sales process for customers.
The project completion rate has reached more than 10% of the foundations and structural frame.
Date
01/08/2022
The main contractor for the project has been contracted.
The structural work has been completed, the project features have appeared, and internal work has begun, establishing central air conditioning , plumbing, electricity, and the smart home system.
The contract with the main contractor for the project has been completed, and the plans and designs have been delivered to start work and deliver the project schedule.
Date
01/07/2022
The design, plans and visual identity of the project have been completed.
The project is being constructed according to the highest international specifications and tests are being carried out to ensure the best results are provided. The construction rate has reached 50% for the structural structure and finishing work has begun.
The design and planning phase has been completed. This project follows the series of Al-Thiqa Villas projects in its third phase. This project is distinguished by the use of multiple spaces and gardens.
Date
25/06/2022
Land was acquired in Al Rawdah district in Dammam
The works agreement was signed with the main contractor, Knowledge and Planning, which is a subsidiary company, to start the works, receive the plans, and inspect the project site to carry out the initial work on the project.
A plot of land was acquired in Al Rawdah district in Dammam, along the most important roads in the Eastern Province, Dhahran-Jubail Road. This district is located in the middle of Dammam, closer to Al Khobar and King Fahd International Airport, with an area of 1262.5 square meters, to build 4 villas with an exceptional design.