The project completion rate reached 85%.
As an extension of our ongoing work and in the most important promising areas in the city of Al-Khobar on the New Corniche Road and the waterfront, the fourth phase of Trust Villas was launched, as it is close to the sea and to the most important commercial centers, Al-Jawhara Mall, and Saudi entertainment projects. The project was designed to take advantage of the multiple spaces and gardens, as well as (Sky Light). .
The project completion rate reached 85%.
Accordion Content
The percentage of work in the Al-Thiqa Villas Project, Phase Four, has reached 85%, as the project’s external facade work has been completed, and the project will be delivered at the beginning of the fourth quarter of 2023.
Date
08/15/2023
The project completion rate reached 65%.
Accordion Content
The percentage of work in the Al-Thiqa Villas Project, Phase Four, reached 65%, as the facade work is almost complete, the air conditioning and electrical work has been completed, and 25% of the project has been reserved.
Date
05/18/2023
Finishing and interior works have reached 50% and reservations have started
Date
03/05/2023
Date
02/15/2023
The structural completion rate reached 80% and the interior works have begun.
Date
01/01/2023
The project completion rate reached 15%.
Thank God, the show apartment was inaugurated in the Al-Thiqa Residential Complex and Sales Center project, in preparation for receiving customers and receiving reservations. At the same time, a Wafi license (off-plan sales) was issued, as the company was qualified to be one of the most important companies in the region and to facilitate the sales process for customers.
The project completion rate reached more than 15% of the foundations and structural structure.
Date
11/30/2022
The main contractor for the project has been contracted.
The structural work has been completed, the project features have appeared, and internal work has begun, establishing central air conditioning , plumbing, electricity, and the smart home system.
The contract with the main contractor for the project has been completed, and the plans and designs have been delivered to start work and deliver the project schedule.
Date
01/11/2022
The design, plans and visual identity of the project have been completed.
The project is being constructed according to the highest international specifications and tests are being carried out to ensure the best results are provided. The construction rate has reached 50% for the structural structure and finishing work has begun.
The design and planning phase has been completed. This project follows the series of Trust Villas projects in its fourth phase. This project is distinguished by the use of multiple spaces and gardens, as well as (skylight).
Date
10/25/2022
Land was acquired in Al Bahr district near the new seafront.
The works agreement was signed with the main contractor, Knowledge and Planning, which is a subsidiary company, to start the works, receive the plans, and inspect the project site to carry out the initial work on the project.
A plot of land in Al Bahr district opposite the new waterfront in Al Khobar with an area of 1200 square meters was acquired to build 4 villas with an exceptional design.